Travaux de construction et travaux spéciaux

Safiec dragage1

CENTRAL THERMIQUE SAFI 2019-2020

Dredging of the seawater intake basin of the SAFI thermal power plant.

  • Volume 69 624 m3.
  • Maintenance dredging.
  • 3 months (from June 2020 to August 2020)
Tarfaya_Album

TARFAYA MAROC 2019

Dredging and rock excavation works to improve access conditions to the port of Tarfaya 599,590 m3.

  • Volume :599 590 m3.
  • 08 months (from January 2019 to August 2019).
  • Dredging / Rock digging.
Tarfaya_Album

MARCHICA 2018

Dredging and rock excavation works to improve access conditions to the port of Tarfaya 599,590 m3.

  • Volume :599 590 m3.
  • 08 months (from January 2019 to August 2019).
  • Dredging / Rock digging.
tantan

MARCHICA 2018

Massive dredging works in the port of TANTAN.

7 months (August 2014 to March 2015)

  • Volume 2 305 211 m3.
  • Massive maintenance dredging.
IMG1

Remplissage de plage de sable MAROC 2011

  • Remplissage de plage de sable

quaienacier

LARACHE MAROC 2010-2011

  • Construction d’un quai en pieux d’acier (276 ml)

IMG

CASABLANCA MAROC 2009

  • Utilisation d’un marteau pneumatique de 10 tonnes, version sous-marine